O&C Refurbishment for Orion

The Operations and Checkout (O&C) facility at Kennedy Space Center was originally built to assemble the Apollo capsule.  When NASA announced the development of the next generation Orion Crew Exploration Vehicle (CEV), Space Florida stepped up and provided the $35 million necessary to refurbish and modernize the O&C.  Working closely with the Orion contractor, Lockheed Martin, Space Florida has assured that the CEV will be built and refurbished in Florida for many years. 

 

Project Details

$35 million appropriated by the State of Florida

Project earned the Golden Eagle Award for Excellence from ABC

Completed on time and under budget

900 people were, at some point, directly involved in the project

59 of the 70 subcontractors and vendors were Florida-based

Impacts

An average of 100 direct, full time jobs were created during the construction

Will lead to an estimated 300 full time jobs when fully operational

Modifications and upgrades were desi